Thursday, October 22, 2009

Project Update

Help Desk Relocation

Close-Out report as well as lessons learned being finalized. Draft has been completed and will be reviewed by the FIP Team Oct. 29 and then distributed to appropriate MC IT Groups for consensus.

Temporary Help Desk Area Back fill

Requisition has been sent to Network Engineering for submission. Network Engineering has decided on additional modifications, per N/E Director and NOC Manager. Revised design is now being developed and will be completed within the next week and sent back to N/E for approval.

Takoma Park Data Center (IT Operations Center)

Contract has been closed out and the Project Close-Out Report is in development. IT Operations Center is now in operational status.