Tuesday, June 30, 2009

Project Update

Help Desk Relocation - The IT Help Desk has been moved from it's temporary position within the Cafritz IT Area into it's permanent location within the Takoma Park Data Center. Successful operation has continued for the last 25 days and no issues have been reported.Temporary Help

Desk Area Backfill - Design modifications to take advantage of excess furniture are ongoing. Final design and quote expected by Mid-July and requisition to be submitted to procurement shortly thereafter.

Takoma Park Data Center - Completion of activities related to the CRAC units is ongoing. Arica/JMT/Central Facilities are working to resolve these issues by the end of July. FIP will be monitoring these activities as they progress.

Tuesday, June 2, 2009

Project Update

Help Desk relocation to it's permanent location will begin on June 4th and be complete by COB June 5th.

Help Desk Backfill design has been returned to the vendor for modification. Upon correction the req will be placed with N/E for processing.

Network Engineering relocations to the Cafritz building from the Rockville data center and OITB will begin mid July and continure until migration of the Rockville Data Center applications has completed in winter 2009.