Commissioning issues are wrapping up. Some tweaking of the CRAC units is being completed by the vendor.
Help Desk Relocation is set to begin June 1st and complete by June 5th. This move will be from the temporary location to it's permanent location within the IT Ops Center.
Help Desk Backfill design is still in development with the furniture vendor. The first design was sent back for revision.