Wednesday, December 24, 2008
December 24, 2008
Rack power distribution cabinets are being installed. Contractor is performing finish work on all areas. Facilities will be performing a punch list walk through with Contractor to address any discrepancy's.
Wednesday, December 3, 2008
December 3, 2008 - Project Update
Delivery of racks has been completed and floor stands for main PDU's as well as FDCs (PDU's that sit the end of each row) have been installed. Delivery and installation of these units will take place over the next two weeks. Construction activities are nearing substantial completion and commissioning of the space is ongoing.