Monday, September 29, 2008

September 29, 2008

Raised access floor within the Equipment Room itself has been substantially completed. Ceiling finishes as well as finishes within the Monitoring Area have been started as well. Cable tray both under floor as well as ceiling trays have been installed. Arica currently is awaiting delivery of the PDU's as well as racks for the equipment room.