Thursday, April 3, 2008
The operation center’s floor has been stripped of the previous floor. This exposed several large core drilled holes, diverse flooring (brick and different kinds of concrete), and many uneven surfaces. The JMT group took pictures and is working to design a compressive way to seal the different holes and level the floor. This design/plan should be done in the next seven to ten working days. In the mean time work continues on the in build electrical work to support both the operations center and the helpdesk. Help desk Walls are up and most of the electrical wiring for the area is in place. The walls cannot be finished until permits are in place and MC is working to get these done.