Wednesday, June 2, 2010
Project Update
Review of final report ongoing. Corrections and final distribution to IT groups within the next 2-3 weeks.
Tuesday, March 23, 2010
Project Update
Review of Project Update has been scheduled for the second week of April. This will be a FIP review and upon final review will be distributed to IT Groups for review and comment.
Wednesday, February 24, 2010
Project Update
Due to unforseen scheduling issues completion of the review process has been pushed out to Mid-March.
Monday, January 11, 2010
Project Update
Help Desk Relocation
Awaiting approval from IT Groups on Close-Out Report.
Temporary Help Desk Area Backfill
Awaiting authorization by college administration.
Awaiting approval from IT Groups on Close-Out Report.
Temporary Help Desk Area Backfill
Awaiting authorization by college administration.
Tuesday, December 1, 2009
Project Update
Help Desk Relocation
Awaiting final approval from IT Groups on Close-Out Report.
Temporary Help Desk Area Back fill
Requisitions prepared and awaiting signature by N/E.
Awaiting final approval from IT Groups on Close-Out Report.
Temporary Help Desk Area Back fill
Requisitions prepared and awaiting signature by N/E.
Thursday, October 22, 2009
Project Update
Help Desk Relocation
Close-Out report as well as lessons learned being finalized. Draft has been completed and will be reviewed by the FIP Team Oct. 29 and then distributed to appropriate MC IT Groups for consensus.
Temporary Help Desk Area Back fill
Requisition has been sent to Network Engineering for submission. Network Engineering has decided on additional modifications, per N/E Director and NOC Manager. Revised design is now being developed and will be completed within the next week and sent back to N/E for approval.
Takoma Park Data Center (IT Operations Center)
Contract has been closed out and the Project Close-Out Report is in development. IT Operations Center is now in operational status.
Close-Out report as well as lessons learned being finalized. Draft has been completed and will be reviewed by the FIP Team Oct. 29 and then distributed to appropriate MC IT Groups for consensus.
Temporary Help Desk Area Back fill
Requisition has been sent to Network Engineering for submission. Network Engineering has decided on additional modifications, per N/E Director and NOC Manager. Revised design is now being developed and will be completed within the next week and sent back to N/E for approval.
Takoma Park Data Center (IT Operations Center)
Contract has been closed out and the Project Close-Out Report is in development. IT Operations Center is now in operational status.
Monday, September 14, 2009
Project Update
Help Desk Relocation
Close-Out report as well as lessons learned being finalized. Draft has been completed and will be reviewed by the FIP Team Sept. 18 and then distributed to appropriate MC IT Groups for consensus.
Temporary Help Desk Area Back fill
Final design and quote received. Project pending direction by Central Facilities due to possible inclusion within college FY10 project plan. No direction yet from Central Facilities as to when this project will occur.
Takoma Park Data Center
Project has been closed out and the Project Close-Out Report is being developed.
Close-Out report as well as lessons learned being finalized. Draft has been completed and will be reviewed by the FIP Team Sept. 18 and then distributed to appropriate MC IT Groups for consensus.
Temporary Help Desk Area Back fill
Final design and quote received. Project pending direction by Central Facilities due to possible inclusion within college FY10 project plan. No direction yet from Central Facilities as to when this project will occur.
Takoma Park Data Center
Project has been closed out and the Project Close-Out Report is being developed.